BGC Mining / Atlas Iron – Mt Webber – Iron Ore

Project BGC Mining / Atlas Iron – Mt Webber – Iron Ore
Client BGC Mining / Atlas Iron
Contract Period Mar 2014-Jul 2014; Stage 2: Aug 2014-Jan 2015; Maintenance: Jan 2015 - April 2015
Contract Type Stage 1 & 2 Maintenance
Status Completed
More Info Read Here

Contracted to BGC Mining Projects

Stage 1

Interquip assisted BGC Mining Projects in the installation of a 3mtpa crushing circuit for their client, Atlas Iron at Mt. Webber.
Project works commenced in March 2014 and were completed in July 2014.

Stage 2

Interquip assisted BGC Mining Projects in the installation the crushing circuit (Stage 2).
Works commenced in August 2014 and were completed in Jan 2015).

Maintenance Works

All works were completed on time and Interquip Construction had a presence on site with ongoing maintenance of the crushing circuits from Jan 2015 until April 2015.